**Please note that Downtown St. Thomas is open for business via. Talbot Hill, Wellington Road, Stanley Street and Elgin Street. Talbot Street will remain open for the duration of the project.
Work Involved
- Remove existing asphalt and concrete, and installation of new watermain and sanitary sewers within the City right-of-way for full road reconstruction along Sunset Drive adjacent to Fingal Line/Talbot Street
- Construction of 2 new sewage pumping stations on Wellington Road and Sunset Drive (in V.A. Barrie Park)
- Installation of sewage forcemains along Wellington Road and Sunset Drive.
- Restoration of driveways and other areas in City right-of-way as needed.
- Restore with topsoil and sod in disturbed lawn areas
- For more information please view the Project Construction Drawings
Timeline
- Project will commence mid June 2022, with the full road reconstruction along Sunset Drive
- As the road reconstruction is being completed, directional drilling for the sanitary forcemains will be done along Wellington Road and Sunset Drive.
- All road works, sanitary forcemains and sewers, and watermains will be completed by May 19, 2023.
- Pumping Stations will also start at the same time as the road reconstruction with the completion day of those works by July 2023.

For more information please see the Project Construction Drawings